This function calculates the number of working days between two dates. The calculation is based on the table of non working days.
This function calculates the number of working days between two dates. The calculation is based on the table of non working days in PdC.


== Code example ==
== Code example ==
Line 16: Line 16:


== Availability ==
== Availability ==
Available since April 2014 (from version 4.3)
Available since 2011 (from version 4.1)

Latest revision as of 14:55, 22 April 2014

Declaration

NoOfWorkingDays(StartDate, EndDate as Date) as integer

Description

Returns the number of working days between two dates.

Notes

This function calculates the number of working days between two dates. The calculation is based on the table of non working days in PdC.

Code example

This example returns the number of working days of the following seven days from now. Normally the answer is 5.

  msgbox pdc.NoOfWorkingDays(Date(), Date() + 7)

Availability

Available since 2011 (from version 4.1)